The progress is still going strong.
DRAG STRIP - The concrete pouring for the 1/4 mile portion of the track should be finished this week. Then the pouring of concrete for the shutdown will continue. YES CONCRETE SHUTDOWN. No more transitions.
ROAD COURSE - The grading is done. The curbing and barriers are going up.
Where staging lanes will be
![]()
From under the tower
![]()
![]()
From the end of the current wall to the tower
![]()
From 1/4 toward the end of the track - New light poles are in. The new walls to the end of the track is starting to go Yes there will be a wall on the right side.
![]()
![]()
The return road.
![]()
From The end of the track
![]()
![]()
![]()
Road Course
![]()
![]()
![]()
![]()